From:                              Morgan, Denise

Sent:                               Monday, November 14, 2011 1:32 PM

To:                                   Maples, Margie

Subject:                          FW: EHS - Change Order

 

Can we get this on the board agenda?

 

From: Bob Kelly [mailto:bob@studiolcarchitects.com]
Sent: Monday, November 14, 2011 1:27 PM
To: Morgan, Denise
Subject: EHS - Change Order

 

 

 

Denise

 

I had assumed it was too late to submit a change order for next Monday's board meeting.  Nate suggested that I go ahead and send the info to you.

 

This Change Order covers re-hanging the light fixtures in the Computer Server Rooms and Gymnasium Lobby per the current Building Code.  The fixtures had previously only been supported by the ceiling tile grid.  The fixtures are now attached to the roof structure as an added safety precaution called for in the code.

 

This will be Studio LC Change Order # CO 010.  The Change Order amount is $5017.00.

 

I will forward the AIA G701, the KDE Supplemental form, and supporting documents a little later this afternoon when I finish completing the forms.

 

I am currently expecting three more change orders to be submitted by Marrillia that I have previously mentioned to the board.  Marrillia, however, has not yet submitted the paperwork to me for those to be executed.

 

 

 

 

Regards,

 

Bob Kelly, Project Architect

 

Studio LC Architects, LLC

 

bob@studiolcarchitects.com

 

859 327 5745

 

 

 

Warning: This email may contain confidential or privileged information

 

intended only for the use of the individual or entity to whom it is

 

addressed. If you are not the intended recipient, please understand

 

that any disclosure, copying, distribution, or use of the contents

 

of this email is strictly prohibited.