Rationale:
Craig Aossey, Architect of G. Scott & Associates, Architects PLC shares:
This project will be broken down so the total bid amount will be divided between a contract with Derek construction and a few Direct Purchase Orders for materials (this saves you from paying sales tax on those materials). For this reason, the Board action will include approval of the contract amount with Derek Engineering and multiple Direct Purchases that when added to that contract amount, total the bid amount. I have written two options for the Board Action below. One with you accepting Alternate #1 and one with you not Accepting Alternate #1 (neither recommendation accepts Alternate #2).
A memo with further details is attached for your review. The bid tabulation sheet is also included.
Sample Board Actions:
Option #1 with Alternate #1:
“Move to accept Base Bid plus Alternate #1 from Derek Engineering for the Anchorage Independent School Innovation Lab Renovations, at a total cost of $185,750; to execute a contract with Derek Engineering in the amount of $146,820.00 for installation; to issue Direct Purchase Orders totaling $ 38,930.00 (separately listed below); further to submit a revised BG1 to KDE to reflect the current project values.”
US Specialties Holding Company $22,490.00
Echo Electric Supply #1 $6,300.00
Echo Electric Supply #2 $10,140.00
Option #2 with No Alternate:
“Move to accept Base Bid and no Alternates from Derek Engineering for the Anchorage Independent School Innovation Lab Renovations, at a total cost of $184,790; to execute a contract with Derek Engineering in the amount of $145,860.00 for installation; to issue Direct Purchase Orders totaling $38,930.00 (separately listed below); further to submit a revised BG1 to KDE to reflect the current project values.”
US Specialties Holding Company $22,490.00
Echo Electric Supply #1 $6,300.00
Echo Electric Supply #2 $10,140.00 |